Market globalization has in effect led to
increased competition, not just between companies , but also on a macro level
between individual countries , keeping cost low with traditional cost
management has been a commonly applied measure to improve competitiveness.
Value Engineering (VE) is a practice whose
goal is, always, to achieve value for money. VE found its first applications in
U.S.
manufacturing at the end of World War II. Its introduction to construction in
the early 1960s was fueled by the U.S.
military and expanded throughout the U.S. government. Subsequently, its
use has spread globally.
The report goes beyond merely describing
the theory of VE in order to explain how the methodology can be productively
used in practice . it is hoped that the practice advice contained in its
chapter will assist engineers , who are involved with establishing VE
activities within their organization , it also aimed at assisting all those who
may become involved with VE to participate more productivity by giving them
greater appreciation of the basics of VE , and how it relates to other
construction activities.
By applying VE
job plan on case study (1) a factory for ready made garments in New Borg El
Arab Industrial Zone, VE team saved a 8.9% of total cost of the project.
And saving 4.15%
of total cost by applying it on the skeleton and bricks only for case of study (2) ,
it is for a residential, commercial building (Cleopatra
Plaza ) located at Al Azarita – Alexandria .
Selecting the
project at the appropriate stage of development (the timing of the study) is
very important to the success of the VE study. Value can be added by performing
a VE study at any time during project development